Managing Stage Boundaries
From IT frameworks
Contents |
Managing Stage Boundaries (SB)
Purpose & Description
- This process ensures a controlled end of a stage, and planning for the next
- This process is normally triggered once by IP and several times by CS depending on the size of the project
- The Project Manager carries out the process’ activities in preparation for the Project Board’s go/no go decision
Objectives
- To assure the Project Board that the previous stage has been completed as agreed
- To provide information to the Project Board confirming that the project still is viable
- Produce a Next Stage Plan
Inputs
- PID
- Project Plan
- Stage Plan
- Business Case
- All project logs
Outputs
- Next Stage Plan
- Exception Plan
- End Stage Plan
- Updated Project Plan
- Updated project logs
- Updated Business Case
Hints and Tips
- Remember to include both internal and external products in the NSP
- Always update the logs actively. They are of great value during and after the project