Managing Product Delivery
From IT frameworks
Contents |
Managing Product Delivery (MP)
Purpose & Description
- This process allows a controlled break between PM and the Team Manager
- This process is triggered by CS and may/should use PL
- The process needs to be set up as appropriate for the project, in order to avoid unnecessary bureaucracy
Objectives
- To agree the work to be done with the PM
- To do the work
- To deliver the product back to the PM
Inputs
- An agreed Work Package
Outputs
- Updated Risk Log
- Updated Quality Log
- Completed Work Package
Hints and Tips
- Create procedures to keep the PM updated on progress
- Adjust the process to fit the project, not the other way around