Setting up Project Files is the fifth sub-process of the PRINCE2 process Initiating a Project
| Type: | Initiating a Project |
|---|---|
| License: | GPL |
| Frameworks: | PRINCE2 |
| Contributors: |
Contents |
Purpose
The purpose of this sub-process is to ensure that a sensible and efficient project filing system is in place.
Trigger
This sub-process follows after IP4.
Input to the process:
Product
Completing IP5 will generate the following products:
- Issue Log
- Lessons Learned Log
- Updated Project Quality Plan
Critical success factors (CSF)
Key performance indicators (KPI)
Roles
- Owner: Project Manager
- Manager: Project Manager
- Other:
Best practice shows that the Owner and the Manager roles should be merged
Activities
Definitions
Putting into use
Best practice
Challenges and solutions
References and resources
- Managing Successful Projects with PRINCE2