End Stage Report
From IT frameworks
Purpose: To give a summary of progress to date, the overall project situation and sufficient information to ask for a Project Board decision on what to do next with the project. The Project Board will either approve the next stage, ask for more risk assessments or say stop.
The report should contain at least references to:
- Current Stage Plan
- Stage plan situation
- Performance against stage tolerances/appetite
- Project Forecast
- Project Plan forecast
- Business Case review to ensure alignment
- Risk review and update as appropriate
- Statistics
- Project Issue situation
- Quality statistics to ensure alignment
- Other events
- Any events that affected stage performance